#1 | |
|
1976 Toyota Corona years forever!
"Wayne"
Nov 2006
Saskatchewan, Canada
22×7×167 Posts |
From my current Worker Window.
Quote:
At this rate I would estimate about 16 more hours. However the status window gives a completion date of Tues Nov 11 at 7:30 AM. I already checked my computer clock. It does say Nov 6 today as is evident in the last update above. Am I reading this wrong OR is this a bug? |
|
|
|
|
|
|
#2 |
|
"James Heinrich"
May 2004
ex-Northern Ontario
3·5·227 Posts |
Possibly the ETA is based on factoring up to 2^70:
11.3% (2^69) / 0.84%/hr = 13.45hr 100% (2^70) / 0.42%/hr = 238hr 251hrs = 10.5 days... hmm, no, that's not right either... PrimeNet shows you have the exponent signed out for LL testing, not just TF... so your TF will have to complete up to whatever level (2^69?), then P-1, then LL... are you sure it's 11-Nov-2008? I wouldn't be surprised if P-1+LL could take ~370 days... |
|
|
|
|
|
#3 | |
|
1976 Toyota Corona years forever!
"Wayne"
Nov 2006
Saskatchewan, Canada
22·7·167 Posts |
Quote:
Code:
v4_computers 0 50324467 LL 0.00% 2008-10-27 17:27 11 2008-10-29 00:38 2008-10-30 00:38 2008-11-07 00:38 0 and it says 2008-11-07 The report that said Nov 11 is the Test ... Status ... dialog right from the PC itself. |
|
|
|
|
|
|
#4 |
|
1976 Toyota Corona years forever!
"Wayne"
Nov 2006
Saskatchewan, Canada
22·7·167 Posts |
Well it finished today as I expected ... so I guess my own status report was wrong.
|
|
|
|
|
|
#5 |
|
Oct 2008
California
22·59 Posts |
sometimes i find prime95 has inaccurate estimates. for instance, once an exponent was estimated by me to finish at 9:10 on a certain day. it was 99% done. initially, prime95 estimated finishing in two days. when it was 99.8% done, it estimated 10:10. 99.9%, 9:30. and as it got closer to the completion it kept revising until it finished at 9:09 which was close to my original estimate...i'm also curious to how prime95 calculates completion dates, since some people like me don't leave their computer on 24/7
|
|
|
|
|
|
#6 | |
|
Account Deleted
"Tim Sorbera"
Aug 2006
San Antonio, TX USA
17·251 Posts |
Quote:
|
|
|
|
|
![]() |
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How many ecm curves per B1 is a good estimate? | EdH | Factoring | 45 | 2013-10-23 13:39 |
| Benchmark Estimate | Primeinator | Information & Answers | 8 | 2009-06-11 23:39 |
| Estimate the new primes | davieddy | Lounge | 34 | 2008-09-17 04:22 |
| A tricky way to estimate pi(x) | XYYXF | Math | 13 | 2006-09-01 15:44 |
| Estimate of sieve duration for 2^811 - 1 | dsouza123 | NFSNET Discussion | 16 | 2004-03-12 15:28 |