When we began the present stage of the Special Project, there were many complaints about how long each curve took and many proposals for working on the smaller factors instead. It's tricky to figure out the consequences of working on smaller factors because of the structure of the algebraic factors. For the next stage, I've built a Planner Page to help track these relationships. It's reachable from the bottom menu of any page on the ElevenSmooth site, or from the upper left navigation box from the Factors page.

Clicking on the "Standard" button shows the standard approach of running 700 curves on the largest number. Every smaller algebraic factor gets 700 indirect curves, and the expected number of primes found is 10.8.

Suppose we skip the largest number, but do 250 curves for each of the five numbers on level 1. Three of the algebraic factors on Level 2 then get only 250 indirect curves - suppose we also do 150 curves for each of these. The total work is then equivelent to only 258 curves on the largest number, and the number of primes expected to be found is 10.4.

This seems like a reasonable approach - 258 equivalent curves, 10.4 primes. Factors missed for the larger composites can be found in a later stage with even higher search limits.

Post alternative suggestions to this thread.
wblipp is offline  
Old 2004-02-17, 02:40   #2
wblipp
 
wblipp's Avatar
 
"William"
May 2003
New Haven

22·32·5·13 Posts
Default

Quote:
Originally Posted by wblipp
The total work is then equivelent to only 258 curves on the largest number, and the number of primes expected to be found is 10.4.
Here's an even more aggressive approach to ignoring the larger composites for this stage. Ignore the Level 1 numbers as well as the top number. Do 150 curves for every Level 2 number. Do enough work on Level 3 to bring every number to 500 total curves (this varies from 50 to 350 direct curves, depending on the composite).

The result is 132 equivalent curves with 10.4 primes. See if you find something even better on Planner Page
wblipp is offline  
Old 2004-02-19, 05:25   #3
wblipp
 
wblipp's Avatar
 
"William"
May 2003
New Haven

22·32·5·13 Posts
Default

I've been thinking about how far we want to go with the various composites. One possilbe guideline is to get the smallest composites to a point where they qualify for NFSNET factoring, and get the other composites to an equivalent level using the ECM Server rule of balancing (length)^2 * (Sum of B1). The NFSNET qualification rule has been "low probability there is a factor under 50 digits." These highly composite Mersenne numbers will probably be best handled using the GNFS, which has been said to be effective through about 165 digits. We should be within those guidelines if we plan on working 200 digit factors 25% of the way through the 55 digit level (B1=110M).

Prime95 does faster multiplcation but must work with larger exponents. Previous work has suggested that for the ElevenSmooth numbers smaller than 15K digits, it is more efficient to use GMP-ECM on the individual composites instead of Prime 95 on the whole Mersenne Number.

By these guidelines, M(3326400) is finished. For the next stage (30 digits, B1=250K) we should do 166 curves on M(163200) and 465 curves on M(1108800). Then we would move on the (35 digits, B1=1M) level and work 54 curves on M(831600). That would end the Special Project, and all remaining work would be done in the ECM Server.

What do you think of this approach?
wblipp is offline  
 

Thread Tools


Similar Threads
Thread Thread Starter Forum Replies Last Post
Special project #2 - Driver escape attempt 2^3*3 schickel Aliquot Sequences 94 2012-03-28 23:35
Special project #3b - Project 400 schickel Aliquot Sequences 307 2011-10-28 01:29
Special project #3a - Project 300 schickel Aliquot Sequences 29 2011-08-12 17:45
Planner for Level 4 of Special Project wblipp ElevenSmooth 1 2003-10-16 22:44
Special Project Level 3 (25 digits, B1=50K) wblipp ElevenSmooth 0 2003-10-15 16:07

All times are UTC. The time now is 01:16.

Mon Oct 26 01:16:14 UTC 2020 up 45 days, 22:27, 0 users, load averages: 1.43, 1.81, 1.84

Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2020, Jelsoft Enterprises Ltd.

This forum has received and complied with 0 (zero) government requests for information.

Permission is granted to copy, distribute and/or modify this document under the terms of the GNU Free Documentation License, Version 1.2 or any later version published by the Free Software Foundation.
A copy of the license is included in the FAQ.