Old 2014-02-26, 13:20   #12
tha
 
tha's Avatar
 
Dec 2002

5·163 Posts
Default

Quote:
Originally Posted by LaurV View Post
Are you sure you used the right format? The Worktodo.add has to follow the same format as the .txt file, i.e. must have [Worker #1] [Worker #2] etc lines.
Adding the [Worker] lines did do the trick transfering the lines properly. If all of them they remain there I will let it know. Thanks for pointing out, I couldn't find any documentation on the worktodo.add option.
tha is offline   Reply With Quote
Old 2014-02-26, 16:38   #13
tha
 
tha's Avatar
 
Dec 2002

5×163 Posts
Default

In all its wisdom mprime added the following line to worktodo.txt file sometime after the succesful worktodo.add manoeuvre :

DoubleCheck=16981FB71096B3709E224E3CFCXXXXXX,32661053,70,1

According to primenet that assignment is not registered to me but someone else. The line was added somewhere inbetween the other lines.

I will throw it out manually and keep watching the worktodo.txt file. I still think we (or at least I) could use an option to set a single worker to 'manual'.

(This could by the way have caused an undesired and unknowingly case of poaching)
tha is offline   Reply With Quote
Old 2014-02-26, 17:36   #14
TheMawn
 
TheMawn's Avatar
 
May 2013
East. Always East.

11×157 Posts
Default

While I was figuring out my manual assignments I also noticed the "reserved to another machine" error which was actually referencing my own machine.
TheMawn is offline   Reply With Quote
Old 2014-02-27, 21:11   #15
tha
 
tha's Avatar
 
Dec 2002

14578 Posts
Default

The [worker] that had the lines added through worktodo.add were deleted by mprime today and replaced by a server assigned DC exponent.

So the only option I have now is to get all my assignments manually. I therefore keep my request for the option to set a worker to manual.
tha is offline   Reply With Quote
Old 2014-02-27, 23:36   #16
TheMawn
 
TheMawn's Avatar
 
May 2013
East. Always East.

11×157 Posts
Default

Did you have "N/A" or an assignment key for the first argument?
TheMawn is offline   Reply With Quote
Old 2014-02-28, 11:21   #17
tha
 
tha's Avatar
 
Dec 2002

5·163 Posts
Default

Quote:
Originally Posted by TheMawn View Post
Did you have "N/A" or an assignment key for the first argument?
Yes.

The lines remain in the worktodo.txt file, mprime just adds a doublecheck assignment in front of it.
tha is offline   Reply With Quote
Old 2014-02-28, 17:38   #18
TheMawn
 
TheMawn's Avatar
 
May 2013
East. Always East.

11·157 Posts
Default

Quote:
Originally Posted by tha View Post
Yes.

The lines remain in the worktodo.txt file, mprime just adds a doublecheck assignment in front of it.
TheMawn is offline   Reply With Quote
Old 2015-12-23, 22:29   #19
petrw1
1976 Toyota Corona years forever!
 
petrw1's Avatar
 
"Wayne"
Nov 2006
Saskatchewan, Canada

2×5×7×67 Posts
Default Trying to save a new thread....Feature Request

PrimeNet Client: Warning if I try to Unreserve an exponent in progress.

Advanced ...
Unreserve Exponent...

I would like it to generate an "Are you sure?" is the the assignment has already started.

I see two cases for this:
1. Accidentally typing in the wrong exponent.
2. What happened to me yesterday: I am running ECM Fermat on all 4 cores of 1 CPU. Because there are NOT a lot of ECM-F work on, odds are there will be duplicates in your worktodo.txt; some active, some not. I had several LARGER future ECM Fermat assignments that were going to take longer than I had expected. So I decided to Unreserve them....but I forgot to notice that there were also 2 of the same ECM Fermat Exponent in Progress (over half done). BUT all instances of that Exponent were unreserved immediately. Future and In-Progress (AARGH!!!)
petrw1 is offline   Reply With Quote
Old 2016-12-15, 17:52   #20
petrw1
1976 Toyota Corona years forever!
 
petrw1's Avatar
 
"Wayne"
Nov 2006
Saskatchewan, Canada

469010 Posts
Default Recent Cleared: Indicate if FIRST factor.

I like the way the Recent Cleared report tells me which Exponents are Factored.

http://www.mersenne.org/report_recent_cleared/

However, with users like TJAOI and kkmrkkblmbrbk looking for and finding so many factors on exponents in general (with or without existing factors) it is much harder to tell which are NEWLY Factored without clicking on each results for that detail.

Don't get me wrong, I have absolutely nothing against them doing that I'd just like a way to know which are NEWLY factored. Any maybe some are interested in those FULLY factored.

I envision either an extra column on the report
OR
A flag on the Type column for example (F; F-First or F-1; F-Fully of F-F)
OR
A check box to Exclude Exponents with an existing factor.

Thanks
petrw1 is offline   Reply With Quote
Old 2016-12-16, 05:30   #21
S485122
 
S485122's Avatar
 
Sep 2006
Brussels, Belgium

32458 Posts
Default

Wring thread, this request should go to the PrimeNet related thread.

Jacob
S485122 is offline   Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Feature request tcharron Software 3 2018-10-03 20:08
Feature request axn Forum Feedback 15 2017-06-03 16:38
"Spare" work feature request Xyzzy Software 0 2009-08-23 06:25
Feature request (Again) JuanTutors Software 7 2008-10-30 00:19
feature request tha PrimeNet 10 2003-12-12 15:37

All times are UTC. The time now is 17:49.


Sun Aug 1 17:49:35 UTC 2021 up 9 days, 12:18, 0 users, load averages: 3.12, 2.31, 1.91

Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2021, Jelsoft Enterprises Ltd.

This forum has received and complied with 0 (zero) government requests for information.

Permission is granted to copy, distribute and/or modify this document under the terms of the GNU Free Documentation License, Version 1.2 or any later version published by the Free Software Foundation.
A copy of the license is included in the FAQ.