Quote:
Originally Posted by Uncwilly View Post
Assuming that you are using v25.8 or later of Prime95:
Prime95 sees that you have more than enough work (days worth), so it will unreserve the work. Here is the fix.

Exit Prime95. Open the Prime.txt file. Add the following line:
UnreserveDays=180
Save the file. Restart Prime95. You now can have ~6 months of work waiting.

Suggestion, use a worktodo.add file to add exponents to your worktodo.txt.
Thanks worked like a charm.

A couple additional questions:
I have an Intel Core 2 Duo E8500 3.16GHz
How many LL test could I queue up for 6 months? 6 tests?

What is the max value I could use for UnreserveDays?

Is there a list of all the parameters and their detailed explanations that could be added to all the config files:
prime.txt
local.txt
worktodo.txt

as well as the parameters you could pass to mprime when it is run from terminal?

I read the readme file with mprime but this did not have this info..

Thanks.