(BTW, I'm describing what I'd do in Prime95. I don't have experience with mprime and don't know the differences in interface.)

The following steps should do what you want, I think (but I'll bet you want them automated):

1. Manually unreserve all assignments in the worktodo file except the one currently in progress. 2. Delete all those (except the one) assignments from the worktodo file, once you've unreserved them. Do #2 only after #1 in case manual unreserving doesn't work (server down, manual results page screwy again, ...).

Or, alternatively, if feasible: Just assign only one exponent at a time to each prime-stuff-doing machine. Assign another only after completion and only if that machine is to continue.