Stop receiving new tasks
 
I am planning to move Prime95 to a new PC, so I would like to let the program finish the current tasks and not receive new ones.

How can I do that?
Thanks!

LookAS 2018-01-18 13:40

Under Options -> Preferences set "0" for Days of work to queue up.

Uncwilly 2018-01-18 13:45

Add NoMoreWork=1 to prime.txt

Make sure you stop and shut down Prime95 first, then restart it.

[url]http://mersenneforum.org/showthread.php?t=22724[/url]
[url]http://mersenneforum.org/showthread.php?t=21494[/url]
[url]http://mersenneforum.org/showthread.php?t=16704[/url]

axn 2018-01-18 14:21

Or just move the entire folder to the new PC and resume crunching...

ATH 2018-01-18 17:21

[QUOTE=Uncwilly;477824]Add NoMoreWork=1 to prime.txt[/QUOTE]

or MaxExponents=0 in prime.txt.